AMP Development — Part-M

Free lesson preview: AMP Development — Part-M

Developing an Aircraft Maintenance Programme under Part-M

Lesson 1 of 15, exactly as learners see it. No sign-in needed; practice answers are not saved.

  • 7.5 hours learning
  • 12 questions, 18 min
  • Certificate at 75 %

Lesson 1 of 15

The aircraft maintenance programme and the rules that shape it

One programme has to serve three different aircraft

On 2026-09-01, Example Regional Airlines asks you to build one aircraft maintenance programme (AMP) for three regional twin-turboprops. Two are new. The leased aircraft has years of service and a repair the others lack. The AMP combines the approved schedule with procedures and standards so planning and maintenance know what applies to each aircraft.

You are the programme engineer at the airline’s own continuing airworthiness management organisation (CAMO), Example Regional CAMO, approval ZZ.CAMO.0031. The Zedland Civil Aviation Authority (CAA) oversees the CAMO and the aircraft register. Zedland, its organisations, aircraft and exhibits are fictional. The case treats Zedland as a Member State.

ERA-AMP-01 issue 1, fleet applicability extract
RegistrationManufacturer serial number (MSN)Entry and configuration
ZZ-ERA1501New, delivered 2027-03-15. Latest modification standard.
ZZ-ERB1507New, delivered 2027-04-20. Extra cargo-compartment smoke detector.
ZZ-ERC1123Lease from Example Leasing. Older standard, antenna modification and aft-fuselage repair. Enters the Zedland register and ERA-AMP-01 on 2027-02-01.

Draft the extra detector task against MSN 1507. Keep the repair inspection against MSN 1123. This is effectivity, the aircraft, parts or configurations to which a requirement applies. Guidance material (GM) M.A.302(a) allows a common programme if it identifies which tasks and procedures apply to each subset. Acceptable means of compliance (AMC) M.A.302 point 2 calls for one approved programme at a time for each aircraft. The outgoing programme governs until transfer.

ZZ-ERC transfers to the Zedland register, ERA-AMP-01 and Example Regional CAMO on 2027-02-01 at 23,800 flight hours (FH) and 27,400 flight cycles (FC). At transfer, the Zedland CAA issues a new Part 21 certificate of airworthiness using a copy of the former certificate and the still-valid incoming airworthiness review certificate (ARC). The former certificate of airworthiness ceases to be valid at the register change.

The first work under ERA-AMP-01 is the bridging check. ZZ-ERC stays on the ground until the check is complete on 2027-02-12. If an incoming ARC remains valid, the receiving authority amends its marks under M.A.905(b)(1)(ii) after the required work. Here it expires during the bridge. The CAMO’s authorised reviewer verifies the new certificate of airworthiness under M.A.903(b)(10). The records show continuous management and compliant maintenance since the former ARC was issued, so the reviewer issues a new ARC on 2027-02-12 under M.A.901(b)(1). ZZ-ERC returns to service on 2027-02-13.

The CAMO sends the new ARC to the Zedland CAA on the issue date. Lesson 14 shows the dispatch record and the recommendation route when the CAMO cannot issue the certificate.

The task list and the rules for using it form the AMP

Open ERA-AMP-01 at its schedule. The A-check is a package of work due every 500 FH or 4 months, whichever comes first. The C-check is due every 5,000 FH or 24 months, whichever comes first. The preface gives the inspection standards and explains who can authorise permitted variations. It excludes tasks whose source sets a maximum gap. Lesson 11 explains how permanent interval changes are handled.

AMC M.A.302 point 1 describes an AMP as the scheduled tasks together with their associated procedures and standard maintenance practices, which it can incorporate by reference. With the preface and task list together, you can identify what to do, when, for which aircraft and under which controls. The maintenance instructions give the detailed method of doing the work.

M.A.301(c) requires maintenance in accordance with the AMP. Under M.A.301(e), the operator’s aircraft also need an analysis of the programme’s effectiveness. When Example Aero Services Ltd, the contracted Part-145 base maintenance organisation, returns work records, the CAMO uses them to update the aircraft’s status and to judge whether the scheduled work is effective. Example Regional Line Maintenance handles line work such as daily, weekly and A-checks. M.A.201(c) makes the person or organisation that performs maintenance responsible for the work it performs.

Choose Part-M or Part-ML before opening a task list

Start with the aircraft’s registration, certification and operation. For aircraft within Article 1(a) of Regulation (EU) No 1321/2014, Article 3(1) sets Part-M as the baseline, subject to the Part-ML categories. If a Part 21 permit to fly was issued, follow its continuing airworthiness arrangements under Article 3(4).

For a third-country registration, check who has regulatory safety oversight. If oversight has been delegated to a Member State and a European Union (EU) operator uses the aircraft, apply the Article 1(a)(ii) and Article 3 analysis above. If oversight has not been delegated and a carrier licensed under Regulation (EC) No 1008/2008 dry-leases the aircraft in, apply Part-T under Articles 1(b) and 3(6).

Article 3(2) places the following other-than-complex motor-powered aircraft under Part-ML, subject to the air carrier exception.

  • Aeroplanes up to 2,730 kg maximum take-off mass (MTOM).
  • Helicopters up to 1,200 kg MTOM certified for up to four occupants.
  • Other European Light Aircraft 2 (ELA2) aircraft, such as sailplanes up to 2,000 kg MTOM and balloons. Check Article 2(ka) for the full definition and the airship conditions.
  • Non-conventional aircraft up to 1,200 kg MTOM if capable of maintaining zero horizontal speed in flight, or up to 2,730 kg for the other non-conventional aircraft.

Article 2(u) classifies aeroplanes as complex if any of its triggers apply. They include MTOM above 5,700 kg, certified passenger seating above 19, a certified minimum crew of at least two pilots, turbojet propulsion or more than one turboprop. Helicopters and non-conventional aircraft have their own criteria. The roughly 23,000 kg Example Regional aircraft qualify on both mass and propulsion. The Article 3(7) relief for specified requirements on multi-turboprop aeroplanes at or below 5,700 kg does not apply.

Part-M applies when an Article 3(2) aircraft is listed on the air operator certificate (AOC) of a carrier licensed under Regulation (EC) No 1008/2008. Before listing, Article 3(3) requires Part-M AMP approval, completion and certification of maintenance due under that approved Part-M AMP in accordance with 145.A.48 and 145.A.50, and a Part-M airworthiness review under M.A.903 with a new airworthiness review certificate under M.A.901 or M.B.901, as applicable. The companion course AMP-DEV-ML teaches how to develop the Part-ML programme.

Read M.A.302 as a set of decisions

Here is the test you apply to the draft before it leaves Example Regional CAMO. The implementing rule sets the obligations. The European Union Aviation Safety Agency (EASA) publishes AMC that show how to meet them. Appendix I to AMC M.A.302 and AMC M.B.301(b) is the detailed reference for the contents and controls of the AMP.

M.A.302 applied to the draft programme
PointQuestion for the engineer
(a)Is each aircraft maintained under an AMP?
(b)Are the issue and its amendments approved?
(c)Does the managing or limited-contract organisation have authority to use its approved indirect procedure?
(d)Which authority instructions, design instructions and Part-26 requirements govern this aircraft? See the source decisions in Lesson 2.
(e)Can we justify proposed escalations or additional instructions, and route safety-related escalations for direct approval?
(f)Does the schedule specify the maintenance, its frequency and the tasks arising from the operation?
(g)For complex aircraft, does an AMP based on Maintenance Steering Group logic or condition monitoring include a reliability programme?
(h)Does review lead to amendments when operating experience or source changes warrant them?

Lesson 11 explains escalation. Lesson 13 shows how the reliability programme tests whether the scheduled work is effective.

Find who can approve the programme

M.A.201(a) assigns continuing airworthiness to the owner. Under (b), those duties pass to the lessee if the lessee is named on the registration document or identified in the lease contract. For Example Regional, (e) makes the licensed carrier responsible. Under (e)(2), its CAMO approval forms part of its air operator certificate. The CAMO develops and controls the AMP under CAMO.A.315(b)(1). The nominated continuing airworthiness manager oversees that work under CAMO.A.305(a)(3). Under M.A.201(d), the airline ensures the pilot or another qualified person carries out a satisfactory pre-flight inspection. List any separate pre-flight maintenance tasks for maintenance staff in the AMP under Appendix I point 1.1.9.

M.A.302(b) requires approval of the AMP and its amendments. Under (c), the CAMO or combined airworthiness organisation (CAO) managing the aircraft can use an indirect procedure if its competent authority approved the procedure in its continuing airworthiness management exposition (CAME) or combined airworthiness exposition (CAE). The same route can cover development and approval processing contracted under M.A.201(i)(3). In either case the organisation needs State-of-registry oversight or a written transfer of AMP approval responsibility under M.1(3).

Take the privately operated, non-complex 3,200 kg aeroplane in Lesson 10. Under M.A.201(i), its owner can contract full management under (1), manage it personally under (2), or retain management and contract just the AMP work under (3).

Limited contract extract. The CAO reviews the programme, drafts changes and processes their approval. The owner gives the CAO current configuration, utilisation and maintenance records. The owner arranges the work and retains the rest of the continuing airworthiness management.

If the same aeroplane starts commercial specialised operations, M.A.201(h) requires full CAMO or CAO management. That point also covers commercial air transport outside licensed carriers and commercial training covered by the rule. Where M.A.803 permits pilot-owner maintenance, record its scope in the AMP.

Use the approved issue and feed the results back

On 2026-12-10 Example Regional CAMO submits issue 1 with the source register, effectivity matrix, compliance checklist and reasons for departures from the sources. Zedland CAA approves issue 1 directly on 2027-01-20. It also approves CAME part 1.2, which covers eligible amendments and excludes the initial issue. Zedland oversees both the aircraft and the CAMO, so no written transfer is needed.

Planning loads the approved schedule and orders the work. Part-145 completes and certifies the work and sends back the records. The CAMO updates aircraft status and uses findings alongside service experience to evaluate the schedule. When a source changes or the evidence points to a problem, the CAMO assesses the proposal and follows the normal approval route before planning activates it. Lesson 13 covers the specific authority authorisation for early implementation. Follow the normal loop in Figure 1.1.

An approved programme keeps taking in new evidenceThe CAMO collects sources and builds the programme, then submits it for approval. After approval, planning activates it. Part-145 performs and certifies the work and returns records. The CAMO reviews the evidence and proposes an amendment if needed. A return arrow sends the amendment back for approval before activation.An approved programme keeps taking in new evidenceCollect sourcesCAMO programmeengineer checks designand authority inputs.Build the programmeProgramme engineermatches tasks to theaircraft and operation.Approve the issueZedland CAA approvesthe initial issue. Eligibleamendments can gothrough the CAMO.Use and recordPlanning orders thework. Part-145 certifies itand returns the records.Propose theamendmentThe continuingairworthiness managerroutes the proposedchange.Review the evidenceReliability engineer andCAMO review findings,use and current sources.applysubmitactivatefeed recordsif neededresubmit
Figure 1.1. The diagram shows the normal approval route before activation. The annual review can start the next amendment.
ERA-AMP-01 revision history extract
EventWhat planning applies
2027-05-26, revision 1 indirectly approvedMandated fuel-system change. The directive’s own action deadlines already govern.
2027-07-16, revision 2 items 1–4 indirectly approvedItem 5 awaits direct approval. The Alternate landing-gear extension functional check stays at 3,000 FH.
2027-10-05, separate direct decision on revision 2 item 5Zedland CAA approves one repeat step to 3,300 FH with sampling. The 3,000 FH first threshold stays in force.
2027-11-08, revision 3Incorporates a change based on service findings and carries forward the earlier item 5 condition.

Maintenance planning document (MPD) revision 15 arrived on 2027-06-14 and the CAMO completed its assessment on 2027-07-09. At the 2028-02-10 audit the new repeat is in force. Lesson 11 gives the sampling and six-repeat conditions, and Lesson 12 shows the release. The first annual review report is signed on 2028-01-18. Compare each aircraft’s actual hours and cycles with the annual bands in Lesson 6. Lesson 15 shows how the CAMO completes that missing comparison.

At work

Before releasing the programme to planning, take one aircraft and follow the decisions it depends on.

  1. Identify the aircraft and operation

    Start with the registration, certified limits and operation. Record the Article 3 decision. Resolve uncertainty before choosing the approval process.

  2. Open the controlled issue

    Match the approval and effective pages to the issue in planning. Trace one aircraft-specific task from effectivity to work order. If the task is missing or linked to the wrong aircraft, establish the affected due position with planning and correct it under your control procedure.

  3. Follow one task back from the hangar

    Look for the accomplishment record, the updated status and the findings used for review. Ask the responsible team to resolve missing evidence before taking credit for the work.

CAMO-AMPR-FAM introduces the programme and reliability functions. CAMO-REL-ADV develops the reliability analysis in depth. CAMO-PLAN works through the planner’s due dates, forecasts and work packages.

Regulatory basis: what this course includes

This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.

Each source and the amendment, edition or decision this course includes
SourceIncluded up to
Regulation (EU) No 1321/2014 — Articles 2 and 3, Annex I (Part-M) and Annex Vc (Part-CAMO)Implementing Regulation (EU) 2026/100 (applicable from 2026-08-07; its Article 3 corrections from 2026-02-13 and 2026-02-22)
Regulation (EU) No 748/2012 — points 21.A.3B, 21.A.7 and 21.A.31Delegated Regulation (EU) 2026/56 and Implementing Regulation (EU) 2026/100 (applicable from 2026-08-07)
Regulation (EU) 2015/640 — Annex I (Part-26): point 26.201 (tyre pressure) and the ageing-aircraft structures points taught (26.300–26.370)Implementing Regulation (EU) 2024/2954 (applicable from 2024-12-22)
Regulation (EU) No 965/2012 — CAT.GEN.MPA.195 and the Part-SPA points taughtthe text applicable on 2026-11-22 (as in the Air Operations Easy Access Rules, revision 24 (2026-03))
AMC & GM to Part-MED Decision 2026/005/R (Issue 2, Amendment 10; file corrected 2026-09-22. Appendix I to AMC M.A.302 and AMC M.B.301(b) was last amended by ED Decision 2023/013/R)
AMC & GM to Part-CAMOED Decision 2026/005/R (Issue 1, Amendment 6)
CS-26 and its GMED Decision 2024/010/R (Issue 5; file corrected 2026-06-17)
AMC-20 (AMC 20-6B, AMC 20-20B, AMC 20-21)Amendment 23 (ED Decision 2022/001/R)
CS-25 Appendix H and AMC 25-19the edition applicable on 2026-11-22
EASA AMP user guide UG.CAMO.00010-002 and compliance checklist TE.CAMO.00011-002the issues dated 2024-11-11

Checked against the official texts on 2026-11-22. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.

Implementing Regulation (EU) 2026/100 applies generally from 2026-08-07. Article 4 gives earlier dates for Article 3(1) (2026-02-13) and Article 3(2) (2026-02-22). The course uses the 2026-08-07 EUR-Lex consolidations of the continuing and initial airworthiness rules, read with the signed amendments. Use Annex III point (1) of Implementing Regulation (EU) 2023/989 for M.A.302(d)(3). The English Part-M consolidation skips that point.

Use the 2025-09 EASA Easy Access edition for AMC M.A.302 and AMC M.B.301. That edition shows Appendix I as published under Executive Director (ED) Decision 2023/013/R. For the later changes to airworthiness reviews and occurrence reporting, use ED Decision 2026/005/R. In its Part-M Amendment 10, paragraph (c) of the AMC on transfer between Member States explains when to complete bridging work. The course also uses Annex Vd (Part-CAO) for the management route in Lesson 10 and Part-145 point 145.A.55 for work records in Lessons 12 and 14. Lesson 6 covers commercial air transport (Part-CAT) recorders, navigation, de-icing and emergency equipment, and selected specific approvals (Part-SPA). The current reference for the Certification Specifications for Large Aeroplanes is CS-25 Amendment 28. The 2023-01 Easy Access CS-25 pages predate it. Lesson 3 uses the historical Amendment 4 version of AMC 25-19 to explain legacy certification maintenance requirement (CMR) stars and identifies the later guidance separately.

Mid-course quiz Ungraded practice

Send one controlled programme for three aircraft

3 questions · Retry freely · Separate from your final exam

Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.

Your scenario · Fictional training example

You are the programme engineer at Example Regional CAMO. The airline is licensed under Regulation (EC) No 1008/2008. You are preparing issue 1 of ERA-AMP-01 for its three Zedland-registered regional twin-turboprops. The second engineer checks the fleet extract and the submission.

Fleet
ZZ-ERA MSN 1501, ZZ-ERB MSN 1507 and leased ZZ-ERC MSN 1123
Extra detector
Fitted on MSN 1507 only, with its own scheduled test
Approval
On 2026-12-10 the CAMO submits issue 1 and its proposed indirect-approval procedure. Zedland CAA oversees the aircraft and CAMO. The proposed procedure covers eligible amendments and excludes issue 1.
How should you show the extra detector test in issue 1?
Compare all answers and explanations

Assign it to the three fleet registrations. — Consider the consequence.
That would order a test on two aircraft without the detector and obscure the true configuration.

Assign it to MSN 1507 in the common programme. — Best choice.
Correct. Planning can identify the applicable aircraft under one controlled issue.

Place it in an additional AMP for MSN 1507. — Consider the consequence.
A separate approved AMP could cover MSN 1507 if it replaced the shared AMP for that aircraft. It adds a second document to control. Here the common programme meets the airline’s brief by identifying MSN 1507 on the task.

Who approves the initial issue in this case?
Compare all answers and explanations

The continuing airworthiness manager on submission. — Consider the consequence.
The CAMO prepares and controls the programme. Its local indirect procedure does not cover issue 1.

The contracted Part-145 base maintenance manager. — Consider the consequence.
The maintenance organisation performs and certifies work. That role does not confer AMP approval.

The Zedland CAA by direct approval. — Best choice.
Correct. The CAMO submits the issue for the competent authority’s approval.

Once maintenance is using issue 1, what evidence belongs in the CAMO review?
Compare all answers and explanations

Accomplishment records, findings, source changes and operating experience. — Best choice.
Correct. They show what was done and whether the programme still covers the fleet’s needs.

Approval letter, effective pages and the next planned hangar slot. — Consider the consequence.
These help control the issue and plan work. They do not show whether the work or its timing remains effective.

Source revisions and maintenance records for MSN 1501 as the production baseline. — Consider the consequence.
The baseline omits differences on the other serials, including the leased aircraft’s configuration and service history.

Sources checked 2026-11-22. Commission Regulation (EU) No 1321/2014, Articles 1, 2(ka), 2(u) and 3, Part-M M.1(3), M.A.201, M.A.301–302 and M.A.901–903, M.A.905 and M.A.803(c), Part-145 145.A.45, 145.A.48, 145.A.50 and 145.A.55, Annex Vd (Part-CAO), and Part-CAMO CAMO.A.305(a)(3) and CAMO.A.315(b)(1). Consolidated regulation. Commission Regulation (EU) No 748/2012, Part 21 points 21.A.174(b)(3)(i)(A), 21.A.181(a)(2) and 21.B.326(a)(2)(i). Consolidated Part 21. Commission Implementing Regulation (EU) 2026/100, Articles 2 and 4 and Annex III point (3), including the Article 3(3)(c) amendment, application dates and airworthiness review provisions. Official amending act. EASA, AMC M.A.201(i)(3), AMC M.A.302 points 1–3 and GM M.A.302(a). Part-M rules and guidance. Appendix I to AMC M.A.302 and AMC M.B.301(b), sections 1–5 (ED Decision 2023/013/R). Signed Part-26 amendment, Annex III point (1). ED Decision 2026/005/R. Part-M Amendment 10, transfer AMC paragraph (c), page 26. Delegated Regulation (EU) 2026/56. FAQ 19061 on procedure scope. CS-25 Amendment 28. EASA Air Operations, revision 24.

Continue with lesson 2: Where scheduled maintenance tasks come from

€99 per seat + VAT where applicable

Get the syllabus by email

Not ready to buy? We email you the printable syllabus, the free lesson and the course page.

Continue?

Help & feedback

Get guidancePrepared answers about buying, learning and certificates.

For questions about lesson content, open Ask Metis inside that lesson.

Submitted feedback is stored. If you request a reply, your reply email is stored.