Lesson 1 of 7

Event review — Engineering data and configuration

Learning objective: Trace an engineering decision from aircraft configuration to the applicable wiring instructions.

A current drawing for the wrong configuration

Table 1. Training document lookup
Document or observationContent and limiting note
Configuration record and surveyCabin change embodied; connector marked R installed. Base connector P is absent.
Diagram indexBase installation → sheet 1, connector P. After cabin change → sheet 2, connector R.
Sheet 2 connection listSupply wire → R cavity 2 → cabin unit. The cavity assignment specifies connectivity, not the assembly process.
Connector cross-referenceP → assembly entry A; R → assembly entry B. Entry B calls for the sealed contact set and its listed crimp and insertion tools.
Assembly entry B, revision noteRevised sealing check applies to R. Read the preparation, assembly and inspection steps with this note; entry A is not an alternate.

Everyday example. There can be current instructions for two versions of a flat-pack desk. A current document can still specify the wrong hardware for the item in front of you.

At an airline maintenance base, an avionics engineer reviews a recurring cabin fault on a transport aeroplane. A harness instruction copied from the base configuration puts sheet 1 and connector P in the modified aircraft’s work pack. The aircraft’s modification record and survey both show R. Like the desk instructions, each sheet belongs to a different version. The engineer records what is fitted before anyone disturbs it, preserving the evidence needed to explain the mismatch. Sheet 2 traces the supply wire to cavity 2. The cross-reference sends R to assembly entry B for the tooling and revised seal check. The corrected instruction cites sheet 2 for connectivity and entry B for assembly.

Who can change the instruction?

Regulation (EU) 2018/1139 Article 9(1) establishes the essential airworthiness requirements. For this maintenance example, Regulation (EU) 1321/2014, Part-145 point 145.A.45(a), requires the organisation to hold and use applicable current maintenance data. Its paragraphs (e) and (g) address precise work-card references and keeping data current. AMC gives an acceptable means of compliance using “should”; implementing rules use “shall”. GM explains the rule and is not an alternative means of compliance.

Table 2. Three different engineering decisions
SituationRequired basis
An existing repair covers the defectCheck its data basis, effectivity and every restriction. Under 145.A.48(c)(4), damage assessment and repair data follow M.A.304 or ML.A.304 as applicable.
A different method carries out the same maintenance task145.A.45(d): use the procedure in the maintenance organisation exposition (MOE), demonstrate equivalent or improved maintenance standards, and inform the instruction's author. AMC1 145.A.45(d) describes demonstration, compliance-monitoring approval and traceability.
A new repair or modification changes the design145.A.45(d) excludes engineering design approval. M.A.304 specifies the permitted data bases. For a new Part-21 repair requiring approval, 21.A.435(b) assigns classification and approval to EASA or an appropriately privileged design organisation. An internal engineering signature needs the relevant approval or other permitted data basis behind it.

M.A.304 includes Agency-approved and design-organisation-approved data, qualifying standard changes/repairs and the applicable Part-21 Light provisions; those alternatives have their own eligibility conditions. Determine which applies before selecting a scheme. Critical Design Configuration Control Limitations (CDCCLs) are airworthiness limitations: AMC1 145.A.45(d) identifies changes to associated maintenance instructions as type-design changes requiring Part-21 or Part-21 Light approval.

Close the discrepancy with evidence

Model record: observed R on the modified aircraft; examined the configuration record, sheet 2 and entry B; found that the pack cites base entry A. Hold the affected assembly step. The Part-145 organisation records the inaccurate instruction through its internal safety reporting scheme and notifies its author under 145.A.45(c). AMC1 145.A.45(c) recommends retaining the correspondence until clarification. The data author resolves applicability; the planner reissues the pack with entry B and its checks. Maintenance then records accomplishment and the appropriately authorised certifying staff determine release under 145.A.50(a). The engineering record supports that decision; it does not replace it.

Regulatory basis: what this course includes

This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.

Each source and the amendment, edition or decision this course includes
SourceIncluded up to
AMC 20-22 (EWIS training), Target Group 3AMC-20 Amendment 23 (ED Decision 2022/001/R) (AMC 20-22 unchanged since ED Decision 2008/007/R)

Checked against the official texts on 2026-11-17. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.

Mid-course quiz Ungraded practice

Event review: Engineering data and configuration

3 questions · Retry freely · Separate from your final exam

Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.

Your scenario · Fictional training example

A work pack for a modified aircraft cites base connector P, but the installed connector is R. Use the document lookup in Lesson 1.

Configuration
Cabin change embodied; connector R installed.
Lookup
Modified sheet 2 → R → assembly entry B; base sheet 1 → P → entry A.
Revision note
Entry B includes a revised sealing check. Entry A is not an alternate.
Which assembly reference should the revised pack use?
Compare all answers and explanations

Entry B, including its revised sealing check. — Best choice.
The R cross-reference selects entry B as a complete process. AMC 20-22 Appendix C, B2–B4.

Entry A, carrying the cavity assignment from sheet 2. — Consider the consequence.
Sheet 2 changes the connector identity; its cavity assignment cannot make entry A applicable to R.

Entry A, with the sealing check copied from entry B. — Consider the consequence.
Combining selected steps from different assemblies is not the listed process. Use the full R reference.

The Part-145 team confirms that the issued maintenance instruction is inaccurate. What reporting action follows?
Compare all answers and explanations

Send the finding to stores for the next materials review. — Consider the consequence.
Stores may need information, but it is not the data-error reporting action in 145.A.45(c).

Keep the finding in the planner’s personal working notes. — Consider the consequence.
Personal notes do not fulfil the internal safety reporting and author-notification requirement.

Record it internally and notify the maintenance-data author. — Best choice.
145.A.45(c) requires recording through the internal safety reporting scheme and notifying the author.

An alternative access method would carry out the same maintenance task. Which basis permits the Part-145 instruction change?
Compare all answers and explanations

A planner’s endorsement after checking the estimated labour saving. — Consider the consequence.
Efficiency is a possible reason for a change, but does not satisfy all the conditions of 145.A.45(d).

The MOE procedure, equivalent or improved standards, and author notification. — Best choice.
These are the conditions in 145.A.45(d); design changes require a different basis.

The supervisor’s endorsement after reviewing the first aircraft’s completion record. — Consider the consequence.
A completed task does not retrospectively establish the required process and maintenance standard.

Continue with lesson 2: Event review — Wire selection and installation constraints

€55 per seat + VAT where applicable

Get the syllabus by email

Not ready to buy? We email you the printable syllabus, the free lesson and the course page.

Continue?

Help & feedback

Get guidancePrepared answers about buying, learning and certificates.

For questions about lesson content, open Ask Metis inside that lesson.

Submitted feedback is stored. If you request a reply, your reply email is stored.