Electrical safety and role boundaries

Scope, sources and author

Objective: Recognise an electrical hazard and preserve safety without unauthorised intervention.

AMC 20-22 Appendix B trace: TG4: rows 1; TG6: rows 1.

Electrical wiring interconnection systems (EWIS) include wires, connections and their installation features, including support and protection. Damage can interrupt a needed function, connect circuits unintentionally, or produce heat and smoke. TG3 supplies electrical engineering knowledge, TG4 performs assigned general maintenance including unit changes, TG5 plans or engineers other work, and TG6 services areas near wiring. This is initial online knowledge training: aircraft-specific demonstrations, competence assessment and individual task authorisation remain with the employer.

EWIS is wiring, connections, supports and protectionA labelled side elevation shows individually insulated wires entering and leaving a supported metal conduit, continuing through a rubber grommet in a frame-web opening, and held by a cushioned clamp on a bolted bracket before entering a mated connector on mounted equipment. A separate insulated bond lead connects an equipment stud to a ring terminal and structural bond stud. Enlarged Detail A shows the grommet groove seated over the cut hole edge; enlarged Detail B shows the clamp from the cable end, with metal band, elastomer cushion and fixing bolt.EWIS is wiring, connections, supports and protectionRepresentative installation with local sections · not to scale Detail A · grommet ×3Frame webElastomergrommetDetail B · support clamp ×3Metal bandElastomer cushionExposed at cutawayFixing boltABInsulated bundleConduitConnectorEquipmentGround or bond pointBond leadSurrounding structure
Figure 1.1. A continuous bundle passes through supported conduit and a grommeted frame opening, then through a cushioned clamp to a mated connector. A separate bond lead ends in a lug secured to structure; actual installation and assessment require the applicable aircraft data.

From power sources to a safe work area

Everyday example. A lamp at home can be dark while still connected to a live supply. Its switch position does not establish that the cable is safe to handle.

In a Part-145 hangar, a general-maintenance technician sees a split cable jacket behind a removed unit on a passenger jet. The dark bay light gives the same limited evidence as the dark lamp at home. It tells the technician only that the light is off. They keep clear and report the cable location. The authorised maintainer uses the wiring diagram to identify the affected circuit and the aircraft maintenance manual (AMM) to establish and verify isolation for that circuit. The bay stays restricted until the specified checks establish a safe condition.

  1. The authorised maintainer identifies the affected circuit and every source addressed by the task: for example, external power, aircraft batteries and supplies from other equipment. Identify stored-energy precautions and the stated waiting or discharge requirements.
  2. Coordinate with the flight deck, ground-power team and other trades. Remove or isolate supplies in the task sequence. Fit the specified locks, tags and aircraft warnings so another person cannot inadvertently restore power. A warning card communicates the restriction; it is not itself an electrical disconnection.
  3. Establish the safe condition using the task's specified checks, equipment and competent personnel. Service staff keep clear of the exposed wiring and report its exact location rather than probing it.
  4. Keep isolation and warnings in the handover. Before restoration, account for people, tools, disconnected items and temporary protection; restore and test in the prescribed sequence after agreement with affected teams.

If a person may be receiving an electrical shock, raise the alarm, summon emergency services and arrange emergency power isolation. Keep others clear; do not touch the person or exposed conductor while the source may remain live. Once electrically safe, follow the emergency dispatcher's instructions. For an unresponsive adult who is not breathing normally, start cardiopulmonary resuscitation (CPR) immediately. Use an automated external defibrillator (AED) as soon as available, following its prompts. Do not wait for a trained responder to begin indicated CPR or AED use; the dispatcher can guide an untrained bystander. Know the local alarm method and emergency number before work starts.

Never use a wire bundle or harness clamp as a handhold, ladder restraint or equipment support: personnel loads can strain supports, insulation and terminations. Smoke, arcing, unusual heat or exposed conductors require the prescribed immediate response and factual reporting. Repeated breaker resets can feed an unresolved fault; switching after a trip follows the aircraft and operator procedure for the actual circumstances.

Source: AMC 20-22 Appendix C, Module A.1; AMC 25.1721 paragraphs 2–3. General safety references: HSE HSG85, safe isolation; Resuscitation Council UK, 2025 adult basic life support guidelines. The isolation sequence above is a worked planning example; the task supplies the actual switching and proving instructions.

Regulatory basis: what this course includes

This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.

Each source and the amendment, edition or decision this course includes
SourceIncluded up to
AMC 20-22 (EWIS training), Target Groups 3–6AMC-20 Amendment 23 (ED Decision 2022/001/R) (AMC 20-22 unchanged since ED Decision 2008/007/R)

Checked against the official texts on 2026-11-17. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.

Mid-course quiz Ungraded practice

Electrical safety and role boundaries

3 questions · Retry freely · Separate from your final exam

Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.

Your scenario · Fictional training example

An open access area contains wiring beside a service task. One cable has visible outer damage, but nobody knows whether the circuit is energised.

Included duties
TG3: electrical/avionic engineering on in-service aeroplanes; TG4: general maintenance/inspection outside wire maintenance, including LRU changes; TG5: other engineering and maintenance planning; TG6: service duties near wiring
Application
Recognise an electrical hazard and preserve safety without unauthorised intervention.
What establishes the damaged cable's safe condition?
Compare all answers and explanations

The circuit isolation and proving steps in the task. — Best choice.
The task addresses supplies, stored energy, isolation and the checks that establish the safe condition. AMC 20-22 Module A.1.

The open breaker position and a warning card on the panel. — Consider the consequence.
A tag warns people; breaker position and a tag do not replace the task's isolation and proving sequence.

The disconnected unit and the extinguished nearby lamp. — Consider the consequence.
Removing a load and seeing a dark lamp do not establish isolation of every relevant source.

Where should the team put the access load?
Compare all answers and explanations

On the bundle after isolating its electrical supplies. — Consider the consequence.
Isolation does not prevent mechanical damage to wiring and terminations.

On the harness clamp after checking fastener security. — Consider the consequence.
Fastener security does not qualify the support for personnel loading.

On the designated platform or access support. — Best choice.
EWIS supports are not personnel supports. Use the proper access equipment. AMC 20-22 Module A.1.

A person appears to be receiving an electrical shock. What is the immediate response?
Compare all answers and explanations

Grip the cable insulation and move the cable clear of the person. — Consider the consequence.
Do not handle the suspect cable while the source may remain live. Use the emergency arrangements.

Pull the person away immediately by the nearest exposed arm. — Consider the consequence.
The casualty may still be in contact with live equipment; a second person could receive a shock.

Raise the alarm, keep clear and obtain emergency power isolation. — Best choice.
Keep clear until electrically safe. Then follow emergency-dispatcher CPR/AED instructions without waiting for trained help. AMC 20-22 Module A.1; Resuscitation Council UK, 2025 adult basic life support guidelines.

Continue with lesson 2: LRU replacement without collateral wiring damage

€55 per seat + VAT where applicable

Get the syllabus by email

Not ready to buy? We email you the printable syllabus, the free lesson and the course page.

Continue?

Help & feedback

Get guidancePrepared answers about buying, learning and certificates.

For questions about lesson content, open Ask Metis inside that lesson.

Submitted feedback is stored. If you request a reply, your reply email is stored.