Electrical safety and role boundaries
Scope, sources and author
Objective: Recognise an electrical hazard and preserve safety without unauthorised intervention.
AMC 20-22 Appendix B trace: TG4: rows 1.
EWIS means Electrical Wiring Interconnection System: the aircraft's interconnecting wiring and associated devices carrying electrical energy, data and signals. It includes connectors, splices, bonding connections, insulation, clamps and identification. CS 25.1701(b) includes wiring inside racks, panels and junction boxes. Its paragraph (c) excludes internals and integral external connectors of equipment qualified under the stated environmental conditions acceptable to EASA, except the equipment covered by (b); it also excludes portable devices outside the type design and fibre optics. The aircraft-side harness still needs protection during a unit change.
Electrical safety before handling or applying power
Electrical current can kill or cause burns. Smoke, arcing, exposed conductors and unusual heat require the prescribed immediate response: keep people clear, raise the alarm and summon emergency assistance. Do not touch a casualty still in contact with an electrical source. Arrange safe isolation through trained, authorised personnel; first aid follows only when the scene is safe and within the responder's training.
Everyday example. An appliance with its switch off may still be plugged into the mains.
In a Part-145 hangar, one team asks for external power on a passenger jet for a cabin check. A technician on another team still has an avionics connector open under a unit-change task card. The blank display is like the switched-off appliance. It gives no information about whether the connector is safe to handle. The technician checks the open card and its isolation instructions with the person controlling power. The request waits until the affected teams can meet the specified conditions for energising.
- Identify the circuit, task and all relevant supplies, including external power, batteries, alternative feeds and stored energy identified by the instructions.
- Use the task's isolation and verification method. Fit the required warnings and controls against inadvertent re-energisation; coordinate with other teams.
- Before power is applied, confirm the required configuration, personnel clearance and warnings. Tell affected teams and use the prescribed power-application sequence.
A tripped protective device may indicate a fault; switching and reset decisions follow the applicable aircraft procedure, since re-energisation can feed that fault.
Keep feet, tools and access equipment off wire bundles and clamps. They support the installation, not people. Record the observed location, symptoms, time and actions, rather than guessing which component failed. These principles implement the safety subjects in AMC 20-22 Appendix C Module A1; maintenance uses applicable current data under 145.A.45(a). General safe-isolation principles are explained by HSE; the responder-safety principle is also explained in Electrical Safety First's first-aid guidance. Aircraft emergency and first-aid arrangements govern the actual response.
Regulatory basis: what this course includes
This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.
| Source | Included up to |
|---|---|
| AMC 20-22 (EWIS training), Target Groups 4 & 5 | AMC-20 Amendment 23 (ED Decision 2022/001/R) (AMC 20-22 unchanged since ED Decision 2008/007/R) |
Checked against the official texts on 2026-11-17. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.
Electrical safety and role boundaries
3 questions · Retry freely · Separate from your final exam
Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.
An open access area contains wiring beside a service task. One cable has visible outer damage, but nobody knows whether the circuit is energised.
- Included duties
- TG4: general maintenance/inspection outside wire maintenance, including LRU changes; TG5: other engineering and maintenance planning
- Application
- Recognise an electrical hazard and preserve safety without unauthorised intervention.
Compare all answers and explanations
Keep people clear and arrange the prescribed electrical-safety response. — Best choice.
Unknown energisation requires the prescribed response and authorised isolation, not exploratory handling. AMC 20-22 Appendix C A1.
Inspect the jacket by hand before requesting the electrical-safety response. — Consider the consequence.
Hand contact can expose the person to shock or burns; secure the scene first.
Use the nearby light switch to establish the cable isolation status. — Consider the consequence.
The light switch does not establish isolation from every relevant source.
Compare all answers and explanations
Personnel loads become acceptable after circuit isolation is confirmed. — Consider the consequence.
Isolation addresses electrical energy; it does not establish mechanical load capacity.
Personnel loads are permitted when the support appears rigid. — Consider the consequence.
Apparent rigidity does not designate an installation as a personnel support.
Personnel loads can damage insulation, supports and electrical connections. — Best choice.
Clamps support the wiring installation, not people. Use designated access equipment; AMC 20-21 section 11(k).
Compare all answers and explanations
The replacement equipment instructions for its routine power-up test. — Consider the consequence.
Routine power-up instructions may not address an unresolved electrical fault.
The applicable aircraft instructions for this event and configuration. — Best choice.
Switching after a trip follows the event procedure, because energisation can feed the fault; AMC 20-22 Appendix C A1.
The previous aircraft instructions for a comparable equipment fault. — Consider the consequence.
A similar symptom on another aircraft does not establish the switching action here.
Continue with lesson 2: LRU replacement without collateral wiring damage
€55 per seat + VAT where applicable
Get the syllabus by email
Not ready to buy? We email you the printable syllabus, the free lesson and the course page.