Event review — Planning work around wiring
Learning objective: Identify wiring exposure created by the sequence and packaging of non-electrical work.
What changed after the inspection?
A hangar check combines floor-support repair, wiring inspection and cabin cleaning. The early wiring inspection is recorded as satisfactory. Drilling is then added above the harness. The structural card is signed, but metal particles are found on a clamp and the pack schedules panel closure before cleaning. Swarf means metal particles from drilling or machining; it can lodge between wires (AMC 20-22 section 6).
| Decision record | Completed example |
|---|---|
| Known facts | The inspection establishes the examined condition before drilling. The later structural signature covers that task; it does not establish the wiring condition afterwards. |
| Uncertainty | The extent of swarf beneath the harness and behind its supports has not been examined. The original protection plan did not cover the added work. |
| Instruction to apply | Use the aircraft's cleaning and inspection instructions for the affected installation. AMC 20-21 section 11(b) explains why wiring throughout the debris field needs protection and subsequent cleaning. |
| Planning action | Keep access available. Arrange assessment of the affected extent, cleaning and inspection with the necessary staff, lighting and equipment. Revise the sequence and name who maintains and removes temporary protection. |
| Completion evidence | The records identify the area examined after the last disturbing task, contamination removed, defects assessed and resolved, and temporary materials accounted for before panel closure. |
Everyday example. Inspecting a carpet before decorators sand the ceiling tells you little about the carpet afterwards.
On a passenger jet at a Part-145 hangar check, the planner compares the signed floor-support drilling card with the earlier wiring inspection card. Metal particles on a clamp show that drilling changed the condition the inspection recorded. The early card is the check of the carpet before sanding. The planner moves panel closure behind cleaning and the required wiring inspection after the last disturbing task. Keep protection in the revised pack because swarf is difficult to remove once it enters a wire bundle.
Who requires the work to be planned?
The EASA chain starts with Regulation (EU) 2018/1139, Annex II, point 1.5: continuing-airworthiness instructions must support the aircraft throughout its life. Regulation (EU) No 748/2012, Part-21, 21.A.7(a), (b) and (d), places development, provision and amendment duties on the relevant design approval holders. For a Part-M aircraft, Regulation (EU) No 1321/2014, M.A.302, governs the aircraft maintenance programme (AMP); CAMO.A.315(b)(1) requires the CAMO to ensure that it is developed and controlled.
The Part-145 maintenance organisation must use applicable current data under 145.A.45(a), accurately transcribe or precisely reference tasks under 145.A.45(e), and plan the necessary personnel, tools, equipment, materials, data and facilities under 145.A.47(a). Its planning must address fatigue and handover under 145.A.47(b) and (c). The final general verification under 145.A.48(c)(1) includes removal of tools and extraneous materials and refitting removed access panels.
These are implementing-rule obligations. AMC 20-21 supplies accepted EWIS maintenance practices. For training, 145.A.30(e) requires the organisation to establish and control competence; AMC5 145.A.30(e)(a) recommends assessing particular training needs and (b) points to AMC 20-22. AMC 20-22 section 2 expressly says there is no direct EWIS-training requirement for TG3–TG8 in its stated context. The selected syllabus supports the organisation's assessment of duties. AMC describes an acceptable means of compliance; GM explains the rules and is not an alternative means of compliance.
Turn the revised scope into executable work
Survey the zone and adjacent installations before grouping tasks. Put protection before drilling, sanding, painting or fluid work. Allocate cleaning and inspection afterwards, and close access after dependent work is complete. Name who fits, checks, hands over and removes each temporary cover. When scope changes, review the physical exposure and resources as well as the labour estimate. Lesson 2 distinguishes a data defect from a permissible method change or a design change.
Sources: AMC 20-21 sections 11(b), 11(k) and Appendix E; AMC 20-22 sections 2, 6 and 8; the regulatory points identified above.
Regulatory basis: what this course includes
This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.
| Source | Included up to |
|---|---|
| AMC 20-22 (EWIS training), Target Group 5 | AMC-20 Amendment 23 (ED Decision 2022/001/R) (AMC 20-22 unchanged since ED Decision 2008/007/R) |
Checked against the official texts on 2026-11-17. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.
Event review: Planning work around wiring
3 questions · Retry freely · Separate from your final exam
Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.
A floor-support repair is added after an early wiring inspection. The work pack still closes the panels before cleaning, and the next shift will continue work above the harness.
- Task sequence
- Inspection signed before added drilling; post-drilling wiring examination remains open.
- Access
- Panels are open; the work area includes a harness below the drilling.
- Protection
- The pack names a fitter for the cover but no monitoring or removal owner.
Compare all answers and explanations
Name who fits, monitors, hands over and removes the cover. — Best choice.
Correct. Named responsibilities cover the whole period of exposure, including transfer and removal. See 145.A.47(a), (c) and AMC 20-21 section 11(b).
Assign fitting and removal to the structural team’s task signatories. — Consider the consequence.
That identifies two endpoints but leaves monitoring and transfer during other trades’ work unresolved.
Give each trade a separate cover until its own task is signed off. — Consider the consequence.
Separate covers do not establish who maintains protection between tasks or accounts for final removal.
Compare all answers and explanations
Update the labour allowance, retaining the existing protection and inspection sequence. — Consider the consequence.
The new activity can change the debris field and timing of the final inspection, not just labour demand.
Add a final inspection, retaining the earlier protection arrangement for the zone. — Consider the consequence.
Detection afterwards does not address whether the original protection prevents the new exposure.
Reassess protection, access, staffing, sequence and the examination after sanding. — Best choice.
Correct. The new activity affects prevention and final condition. See 145.A.47(a); AMC 20-21 section 11(b) and Appendix E.
Compare all answers and explanations
Completion of the reachable portions, followed by normal closure of the inspection. — Consider the consequence.
Partial examination remains useful evidence, but it cannot complete the expressly required hidden scope.
The missing access and resources, or an acceptable method change under the MOE. — Best choice.
Correct. Meet the issued task or use the 145.A.45(d) procedure with equivalent or improved standards and author notification; it excludes design changes. See also 145.A.47(a).
A shorter inspection scope agreed between the planner and the incoming inspector. — Consider the consequence.
A local agreement does not establish the technical basis or approvals needed for changing the method.
Continue with lesson 2: Event review — Inspection scope, visibility and escalation
€55 per seat + VAT where applicable
Get the syllabus by email
Not ready to buy? We email you the printable syllabus, the free lesson and the course page.