Ignition prevention and maintenance responsibility

Learning objective: Explain why a functioning fuel system can still contain an unacceptable ignition risk.

Start with the work that has changed

A new pump standard, revised inspection or repeated wiring defect is a reason to revisit the protection involved. Bring those changes into this refresher. Appendix IV to AMC5 145.A.30(e) and AMC2 145.B.200(a)(3), section D, says organisations should require recurrent training in each two-year period and update it when relevant instructions change. CAMO Appendix III to AMC4 CAMO.A.305(g) incorporates Part-M Appendix XII, which gives the corresponding continuation guidance.

First check the aircraft scope in the appendix and the person's actual duties. Planning affected maintenance can require the same detailed FTS learning as performing it; relevant component-shop work is included too. Lesson 8 gives the aircraft and role checks. This refresher selects useful concepts and applies them to changes and findings rather than repeating the entire initial syllabus.

What can burn in an apparently empty tank?

Ullage is the gas space above the liquid fuel. Fuel vapour mixes with air there. A mixture can be too lean (too little fuel vapour), within its flammable range, or too rich (too much fuel vapour) to burn. Warming fuel changes vapour generation; changes in tank pressure and temperature alter ignition conditions. A liquid-quantity indication measures neither mixture composition nor oxygen content. Residual fuel can supply vapour after draining.

Ignition also needs a source capable of releasing enough energy under those conditions: an electrical arc, a friction spark or a sufficiently hot surface, for example. A circuit operating normally does not demonstrate its behaviour under a fault. Ignition prevention controls energy sources; flammability reduction controls the mixture's exposure to flammable conditions. These protections complement each other. A published flash point is a fuel test property, not a measurement of today's tank atmosphere or entry clearance. Sources: CS 25.981(a), (b); AMC 25.981(a), 3.1–3.5; CS-25 Appendix N, N25.2(c), (d), (n).

Fuel quantity does not reveal the ignition conditionsA section through a generic metal tank shows fuel at the bottom and ullage containing fuel vapour and air above it. An upward arrow shows fuel supplying vapour. Two aligned columns distinguish the flammable-mixture condition and its flammability-reduction control from a capable ignition source and its ignition-prevention control. A shared statement says potential ignition requires both conditions.Fuel quantity does not reveal the ignition conditionsConceptual tank section — not to scale Tank structure Ullage: fuel vapour + air Supplies vapour Liquid or residual fuel Mixture conditionEnergy conditionMixture in the flammable rangeToo lean or too rich will not support ignition; fuelquantity does not identify the mixture.Capable ignition sourceEnough energy under the conditions: an arc, frictionspark or hot surface.Flammability reductionLimits exposure to flammable conditions.Ignition preventionControls energy sources.Potential ignition requires both a flammable mixture and a capable ignition source.Fuel quantity measures neither mixture composition nor oxygen content; it gives no tank-entry clearance.
Figure 1.1. A conceptual tank section shows gas above liquid fuel, which can continue to supply vapour after draining; flammability reduction controls exposure to a flammable mixture while ignition prevention controls capable energy sources. Neither fuel quantity nor a published flash point establishes the tank atmosphere or entry readiness.

A real investigation: distinguish findings from uncertainty

NTSB/AAR-00/03, adopted 2000-08-23, investigated the loss of a large passenger aeroplane off New York on 1996-07-17. The established event was a centre-wing-tank fuel/air explosion followed by in-flight breakup. Investigators could not establish the initiating ignition source with certainty. They considered a short circuit outside the tank, transferring excessive voltage through fuel-quantity wiring, the most likely mechanism. Keep that distinction when discussing the case: the supported mechanism is likely, not proven. The report's safety concerns support attention to both wiring protection and reducing tank flammability.

From design protection to a maintenance decision

Regulation (EU) 2018/1139 provides the basic airworthiness framework; Article 17(1)(f) and (g) provide for detailed maintenance and continuing-airworthiness-management rules. Regulation (EU) No 1321/2014 supplies the implementing rules (IR): Part-145 145.A.30(e) and CAMO.A.305(g) require organisations to establish and control personnel competence. AMC describes an acceptable way of complying and normally uses should; GM explains the rules and is not an alternative means of compliance. Design approvals under Regulation (EU) No 748/2012, Part-21, determine the aircraft's approved configuration. CS 25.981 is a design certification specification, applied through the certification basis, rather than a universal workshop instruction.

Everyday example. A car starting normally tells you nothing about whether its brakes work.

A Part-145 certifying engineer reviews the ATA 28 card after a pump change on the line. The functional test passes, while the required bonding verification remains unsigned and outstanding. Like the car starting, the pump run demonstrates only the function checked by that test. The bond check answers a separate question about one ignition protection. Keep that item open and request the specified verification and result.

Before release, 145.A.50(a) requires verification that the ordered work was properly performed using the applicable data and that no known non-compliance endangers flight safety.

Regulatory basis: what this course includes

This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.

Each source and the amendment, edition or decision this course includes
SourceIncluded up to
Regulation (EU) No 1321/2014 — Annex II (Part-145) and Annex Vc (Part-CAMO)Implementing Regulation (EU) 2026/100 (applicable from 2026-08-07)
AMC & GM to Part-145ED Decision 2026/005/R (Issue 2, Amendment 9)
AMC & GM to Part-CAMOED Decision 2026/005/R (Issue 1, Amendment 6)
CS-25 and its AMC (CS 25.981 fuel tank ignition prevention)ED Decision 2023/021/R (Amendment 28; file corrected 2025-11-20)

Checked against the official texts on 2026-11-17. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.

Mid-course quiz Ungraded practice

Review the unfinished pump installation

3 questions · Retry freely · Separate from your final exam

Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.

Your scenario · Fictional training example

A pump change reaches shift-end. Its operating test passed, but no bonding-verification result is available. The aircraft was modified since the last similar job.

Task card
Operating test signed; bonding verification open.
Configuration
Modification record has changed since the previous job.
Which conclusion can the supervisor draw from the available test record?
Compare all answers and explanations

Pumping function is demonstrated; the separate protection check remains open. — Best choice.
The checks establish different functions. Obtain the required bonding verification before claiming completion: 145.A.50(a).

The installation is demonstrated by the passing pump test. — Consider the consequence.
The operating check does not establish the separate bonding requirement.

Protection is demonstrated; pumping needs a fresh test. — Consider the consequence.
This reverses the evidence: the pumping test is complete, the protection check is not.

The planner also proposes entry because the tank has been drained. What should change in that plan?
Compare all answers and explanations

Add a repeat quantity-indication check to establish the remaining oxygen condition. — Consider the consequence.
A fuel-quantity indication does not measure oxygen or combustible vapour.

Add the normal operating test to establish atmospheric conditions before entry. — Consider the consequence.
A component operating test does not assess the tank atmosphere or entry protections.

Add the separate assessment of the space and the entry arrangements. — Best choice.
Draining does not establish safe vapour or oxygen conditions. Follow the entry system; HSE INDG258 explains the need for assessment and safe working arrangements.

Which document comparison is needed before copying the earlier pump work package?
Compare all answers and explanations

Compare its labour allowance with today’s staffing and access. — Consider the consequence.
Resources matter, but that comparison cannot establish the technical applicability of the old package.

Compare its effectivity with today’s modification status and fitted pump. — Best choice.
The actual configuration matters under 145.A.45(a), even when the function is familiar.

Compare its completion signatures with today’s certifying-staff authorisation list. — Consider the consequence.
Authorisation checks do not show that the old data still applies to the modified aircraft.

Continue with lesson 2: CDCCLs and configuration integrity

€59 per seat + VAT where applicable

Get the syllabus by email

Not ready to buy? We email you the printable syllabus, the free lesson and the course page.

Continue?

Help & feedback

Get guidancePrepared answers about buying, learning and certificates.

For questions about lesson content, open Ask Metis inside that lesson.

Submitted feedback is stored. If you request a reply, your reply email is stored.