Maintenance Planning for CAMO Staff

Free lesson preview: Maintenance Planning for CAMO Staff

Lesson 1 of 16, exactly as learners see it. No sign-in needed; practice answers are not saved.

  • 7.5 hours learning
  • 12 questions, 18 min
  • Certificate at 75 %

Lesson 1 of 16

The planner's job: from requirement to proven status

On 2026-11-02, you take the planning desk at Example Airways' continuing airworthiness management organisation (CAMO). The records officer has closed the flight totals for narrow-body twin-jet ZZ-EAD at 41,250 flight hours (FH) and 23,180 flight cycles (FC). A heavy maintenance visit is booked for January. Can the main landing-gear bay zonal inspection wait for it?

Due-list extract at the cut-off
Source and taskLast doneLimit and balance
Aircraft maintenance programme (AMP) revision 18, task 32-210, main landing-gear bay zonal inspection21,950 FC21,950 + 1,500 = 23,450 FC. At 23,180 FC, 270 FC remain.

The forecast at induction, when the hangar takes the aircraft in, is 23,530 FC. That is 23,530 − 23,450 = 80 FC past the inspection limit. Find an earlier slot. When the applicable instruction accepts the work and the signed records prove it, record it against the task. That is credit.

The UK Civil Aviation Authority’s Maintenance Interval Exceedances review (2025-06) identifies reported problems in planning, carrying out work and updating records. The gear-bay example follows the work through all three steps.

Know who makes each decision

Who does what at Example Airways
WhoDecision and responsibility
The operatorIs responsible for the aircraft's continuing airworthiness. Operations changes or stops the flying plan when the conditions for flight cannot be met. M.A.201(a) and (e).
The CAMOControls the AMP, airworthiness directives (ADs) and records. Arranges maintenance and checks the return. CAMO.A.315(b).
The Part-145 providerAgrees the scope, plans resources, performs maintenance and certifies the work. 145.A.47 and 145.A.50.

The CAMO checks the approval basis for repairs and modifications, verifies that maintenance meets the AMP and runs a reliability programme where required. Part-145 checks that it has the applicable data. Its authorised certifying staff issue the certificate of release to service (CRS) when satisfied that the ordered work was properly performed and no known non-compliance endangers flight safety.

The continuing airworthiness management exposition (CAME) sets out who acts for the CAMO and how to escalate a limit. The written base maintenance contract sets how the hangar reports new findings and sends back the release and records. The visit work order states the scope for this aircraft. Under CAMO.A.315(d), individual orders can be used for unscheduled line maintenance or component maintenance in the circumstances described in Lesson 11.

When work cannot be completed, Part-145 tells the CAMO. Record the disposition, the decision about what to do with the open item and who acts on it. Confirm a capable replacement slot within the limit before agreeing to remove an eligible unstarted task from the order. If work remains on the active order, use the incomplete-work release route under 145.A.50(c) and (e) in Lesson 11.

Ask the provider for missing evidence. Keep the task open until its completion is proved. Before each departure, the duty planner checks the actual counter and the roster through the arrival at maintenance. Operations blocks a departure that would take that arrival past the limit. It also holds dispatch while the safe condition or applicable status remains unresolved.

Carry one inspection through to proven status

The task master holds the maintenance instruction. The due list applies it to the aircraft’s current counters and last credited work. Forecast when work comes due, then choose the package and confirm a slot with the maintenance provider before sending the order. On return, Records checks the signed card and release and feeds the verified status back into the due list. Follow that loop in Figure 1.1 and in the line-slot records below.

The signed return feeds the next due listThe task master and verified status feed the due list and forecast. Planning selects a package and slot. The CAMO issues the agreed work order. Part-145 performs the work and issues the CRS. CAMO Records verifies the signed return and updates aircraft status for the next due list.The signed return feeds the next due listTask masterVerified aircraft statusDue list and forecastSigned return checkCAMO Records verifies the evidencePackage and slotMaintenance and releasePart-145 performs work and issues the CRSAgreed work orderCAMO issues the ordersets rulesgives statusguides selectionsets scopedefines worksupplies evidenceupdates status
Figure 1.1. The forecast guides the package and agreed work order. Part-145 performs and releases the work, then CAMO Records verifies the signed return and updates aircraft status.

The line slot on 2026-12-24 is 52 days after the snapshot. At 5.0 FC per calendar day, forecast 23,180 + (52 × 5.0) = 23,440 FC. That leaves 10 FC at arrival. Book the inspection in the line package and check the actual roster before flying it.

ZZ-EAD inspection from line order to updated due list
RecordEntry
Line work order LM-1224, line 1ZZ-EAD, AMP rev 18 task 32-210, card Z32-210 issue 3. Inspect both main landing-gear bays. Slot confirmed for 2026-12-24. Forecast 23,440 FC, limit 23,450 FC.
Maintenance returnSigned Z32-210 issue 3. Both bays inspected and access restored. CRS LM-1224-R dated 2026-12-24 at 41,718 FH and 23,440 FC covers LM-1224 line 1.
Records updateCard and CRS matched to order line 1. Last done 23,440 FC. Next due 24,940 FC.

The duty planner checks the roster through the arrival sector against 23,450 FC. Operations holds the first departure after the stop until the release is verified. Records verifies the return and updates the scheduled and out-of-phase maintenance statement in the technical log, or at another location agreed by the authority under M.A.306(a)(3). An out-of-phase task is tracked separately from the normal check sequence. The signed inspection puts the next due point at 23,440 + 1,500 = 24,940 FC. If the same finding keeps appearing, send the cards and usage to the programme or reliability engineer to assess the inspection’s effectiveness.

M.A.305 also requires current status for ADs and immediate safety measures, modifications and repairs, deferred work and defects, life-limited parts and time-controlled components. Current mass and balance is part of the record system.

Meet the fleet and its maintenance providers

Zedland is a fictional EU Member State. The examples use European Union Aviation Safety Agency (EASA) guidance. Its competent authority is the Zedland Civil Aviation Authority (Zedland CAA). The organisations, aircraft and records below are fictional training exhibits.

Organisations at Zedland Central
OrganisationRole
Example AirwaysScheduled commercial air transport operator and air operator certificate (AOC) holder.
Example Airways CAMO, ZZ.CAMO.0012Planning, technical records, technical services, continuing airworthiness manager and airworthiness review staff.
Example Aero Services Ltd, ZZ.145.0417Contracted heavy maintenance hangar. One work order per visit, revised when the scope changes.
Example Airways Line Maintenance, ZZ.145.0021Line maintenance at the main base and two outstations.
Example Engine Services, ZZ.145.0533Contracted shop for engine maintenance and life-limited part replacements.
Fleet forecast rates per calendar day, including idle days
FleetRegistrationsPlanning rate
8 narrow-body twin-jetsZZ-EAA to ZZ-EAH9.0 FH and 5.0 FC
4 regional twin-turbopropsZZ-ETA to ZZ-ETD5.6 FH and 7.0 FC

Keep the forecast separate from verified status

ZZ-EAD was built and received its first certificate of airworthiness on 2012-03-15. The 2026-11-02 snapshot includes flying through 2026-11-01. The log gives 41,088 FH and 23,090 FC on 2026-10-15, when landing-gear AD 2026-T07 took effect. The snapshot records 162 FH and 90 FC more. Use those actuals for past events and fleet rates to forecast future flying.

Each engine has its own hours and cycles since new. Engine 2 came from ZZ-EAB on 2024-06-07, when ZZ-EAD had 18,800 FC. The disk had 14,570 FC since new at installation. Lesson 6 shows how to use those movement records.

A package is a group of scheduled tasks. The Zedland CAA approved the narrow-body AMP, revision 18. Its A-package repeats every 750 FH or 120 days. The C-package repeats every 24 months, 7,500 FH or 5,000 FC. The first applicable limit governs each package. The AMP preface includes the full A-package in each C-package and controls flap-track lubrication separately.

ZZ-EAD package status at the planning snapshot
PackageLast releasedNext limits
A2026-10-27, 41,196 FH and 23,150 FC41,196 + 750 = 41,946 FH or 2027-02-24
C2025-02-12, 35,700 FH and 20,050 FC2027-02-12, 43,200 FH or 25,050 FC

Induction on 2027-01-11 is 70 days after the snapshot. Add 70 × 9.0 = 630 FH and 70 × 5.0 = 350 FC to forecast 41,880 FH and 23,530 FC. At induction the A-package has 41,946 − 41,880 = 66 FH left. The C-package’s calendar limit is forecast to come first, after redelivery on 2027-01-27. Check the roster through the induction arrival against both packages’ limits.

The aircraft stays on the ground during the visit. The CAMO removes line 45, the avionics equipment-bay detailed inspection, in WO-EAD-2701 rev 4 after confirming a capable slot within 41,950 FH. Lesson 11 shows how Planning forecasts the arrival and Operations protects the slot.

The authorised Category C certifier reviews the signed B1 and B2 support summary for WO-EAD-2701 rev 4 to verify that the support staff fulfilled their duties. Under the Part-145 procedure (145.A.30(h)(1)(iii)), the certifier assesses the impact of leaving line 45 unperformed after its removal from the order. The certifier verifies bay restoration on TC-08B and accepts leaving the inspection for the protected line slot within 41,950 FH.

After verifying that the maintenance ordered in rev 4 was properly performed and that no known non-compliance endangers flight safety, the certifier signs the single aircraft CRS, CRS-EAD-270127, on 2027-01-27 under approval ZZ.145.0417. The release references the rev 4 return and the closed seal card NR-001.

After redelivery, Records uses the signed date and counters. For C, the new limits are 2029-01-27, 41,880 + 7,500 = 49,380 FH and 23,530 + 5,000 = 28,530 FC. For A, they are 41,880 + 750 = 42,630 FH and 2027-05-27. The first limit governs each package.

At work

  • Snapshot: aircraft, last flight, cut-off and verified counters.
  • Due row: source and issue, applicable limit, evidence of last work and forecast at the proposed slot.
  • Order: aircraft, line, card issue, booked stop and provider confirmation.
  • Return: matching CRS scope and card, actual counter, next limit and owner of any open action.

Airworthiness Regulations for CAMO Staff covers the organisation's wider duties. Aircraft Maintenance Programme and Reliability explains how to develop and review a programme. Reliability Programme Analysis and Reporting works through the evidence behind a programme change.

Regulatory basis: what this course includes

This course teaches the sources below as amended up to the act or decision shown. Anything published after it is not part of this edition of the course.

Each source and the amendment, edition or decision this course includes
SourceIncluded up to
Regulation (EU) No 1321/2014 — Annex I (Part-M), Annex II (Part-145) and Annex Vc (Part-CAMO)Implementing Regulation (EU) 2026/100 (applicable from 2026-08-07)
Regulation (EU) No 748/2012 — point 21.A.3BDelegated Regulation (EU) 2026/56 and Implementing Regulation (EU) 2026/100 (applicable from 2026-08-07)
Regulation (EU) 2015/640 — Annex I (Part-26): the ageing-aircraft points taught (26.370)Implementing Regulation (EU) 2024/2954 (applicable from 2024-12-22, some points later)
Regulation (EU) No 965/2012 — ORO.MLR.105the text applicable on 2026-11-22 (as in the Air Operations Easy Access Rules, revision 24 (2026-03); Delegated Regulation (EU) 2026/1979, published 2026-11-13, does not change ORO.MLR.105)
Implementing Regulation (EU) 2015/1018 (occurrence lists)Implementing Regulation (EU) 2026/1821 (applicable from 2026-08-17)
AMC & GM to Part-MED Decision 2026/005/R (Issue 2, Amendment 10; file corrected 2026-09-22)
AMC & GM to Part-145ED Decision 2026/005/R (Issue 2, Amendment 9)
AMC & GM to Part-CAMOED Decision 2026/005/R (Issue 1, Amendment 6)
AMC & GM to Part-ORO (ORO.MLR.105)the edition applicable on 2026-11-22 (as in the Air Operations Easy Access Rules, revision 24 (2026-03))
CS-26 and its GM (CS 26.370)ED Decision 2024/010/R (Issue 5; file corrected 2026-06-17)
CS-MMELED Decision 2025/021/R (Issue 4)

Checked against the official texts on 2026-11-22. Before relying on a point at work, check the current consolidated text on EUR-Lex and the AMC & GM currently published by EASA, including any later ED Decision.

Practice decisions

Mid-course quiz Ungraded practice

A line check before the base visit

3 questions · Retry freely · Separate from your final exam

Choose an action, check its consequence and explore the alternatives. Your practice answers are not saved.

Your scenario · Fictional training example

You plan a twin-jet bay inspection for Example Airways. Each sector adds one flight cycle (FC). Follow the case from the initial booking to the proposed roster change.

Due list
Bay inspection due at 18,300 FC. Reconciled counter 18,288 FC.
Arrivals
Main base +11 FC, access confirmed. Outstation +8 FC, access unconfirmed. Base visit +16 FC.
At the initial planning desk, which booking can you confirm?
Compare all answers and explanations

Outstation after 8 FC, subject to proving access. — Consider the consequence.
The projected 18,296 FC fits. Confirm access before accepting the slot.

Main base at 18,299 FC with confirmed access. — Best choice.
18,288 + 11 = 18,299 FC. The station confirms access, so this arrival fits.

Base visit after 16 FC, with hangar access. — Consider the consequence.
18,288 + 16 = 18,304 FC, beyond the inspection limit.

The aircraft reaches main base and the inspection is unstarted. Who owns the roster and order changes?
Compare all answers and explanations

Operations changes the roster. Line Maintenance revises the order. — Consider the consequence.
Line Maintenance confirms the job and slot. The CAMO issues the revised order.

The CAMO changes the roster. Line Maintenance revises the order. — Consider the consequence.
The CAMO controls the work order. Operations changes the roster.

Operations changes the roster. The CAMO revises the order. — Best choice.
Operations changes the flying. The CAMO sends the revised order for the confirmed slot.

At 18,299 FC, the CAMO records a confirmed, capable direct slot at 18,300 FC in the signed amendment removing the inspection. The certifier issues the aircraft release after verifying proper work on the revised order and no known non-compliance endangering flight safety. Operations now proposes an extra sector before the slot. What belongs in the shift handover?
Compare all answers and explanations

Keep 18,300 FC and protect the direct sector. — Best choice.
The two-sector route would reach 18,299 + 2 = 18,301 FC. Operations holds that route before its first departure and keeps the confirmed direct arrival at 18,300 FC.

Keep 18,300 FC. Use the rotation to position for the booked work. — Consider the consequence.
That counts only as far as the first landing. Arrival after both sectors would be 18,301 FC.

Move the deadline to the new booking and retain both sectors. — Consider the consequence.
An agreed change to the order moves the work, but does not change its approved limit.

Sources checked 2026-11-22. Regulation (EU) No 1321/2014, Annex I (Part-M), M.A.201(a), (c), (e), M.A.301, M.A.302 and M.A.305–306; Annex II (Part-145), 145.A.30(h)(1), 145.A.47, 145.A.50 and 145.A.55(a)(2); Annex Vc (Part-CAMO), CAMO.A.300 and CAMO.A.315. EASA Easy Access Rules for Continuing Airworthiness, AMC1 CAMO.A.300 and AMC1 CAMO.A.315(c). Appendix IV to AMC1 CAMO.A.315(c), Contracted maintenance, §§2.14–2.20. AMC1 145.A.50(e), incomplete maintenance. UK Civil Aviation Authority, Safety Performance Indicators, Maintenance Interval Exceedances (2025-06).

Continue with lesson 2: Building the requirement set

€85 per seat + VAT where applicable

Get the syllabus by email

Not ready to buy? We email you the printable syllabus, the free lesson and the course page.

Continue?

Help & feedback

Get guidancePrepared answers about buying, learning and certificates.

For questions about lesson content, open Ask Metis inside that lesson.

Submitted feedback is stored. If you request a reply, your reply email is stored.